Construction Update May 8, 2012

Notices
· “Save-the-Date” Friday, June 1st, 7am-9:30am, for Jackson Hospital’s Grand Open House for all to see the newly renovated Hospital and ER expansion. Dr. Stacy Harbin of Chipola Surgical & Medical Specialties is breakfast keynote speaker; official Chamber of Commerce ribbon cutting set for 9:00am, front lawn.
Work scheduled for this week: (photo shows progress in the renovated Main Lobby)
· Lobby (phase 5) – Final paint, install accessories, install doors and hardware, create punch list.
· MRI – Overhead rough, hang and finish interior walls, start shielding installation, form and pour foundation wall.
· Abate flooring at Pathology, in hallway outside Debbie Matthew’s office. (potentially Wednesday evening)
Two-week Look-ahead:
· Lobby (phase 5) – Final paint, install accessories, install doors and hardware, work off GC punch.
· MRI – Overhead rough, frame interior walls, in wall rough, start shielding installation, form and pour foundation wall.
Updated Frequently Asked Questions about the Renovation & ER Expansion project are available at our website www.jacksonhosp.com, click on the Construction Update button.
|